|
Reproduced from The Times 13 August, 1999
Same principles apply to building cases - law report
Court of Appeal. Stock and Others v London Underground Ltd. Before Lord
Justice Peter Gibson and Lord Justice Pill.
[Judgment July 30]
The principles applicable in a personal injury case, such that, while
some damage must be alleged or proved to succeed in a claim for damages,
the averment of different heads of damage did not give rise to different
causes of action in respect of each head, were applicable in a building
case.
The Court of Appeal so stated in reserved judgment when dismissing an
appeal by London Underground Ltd against a decision of Judge Havery, QC,
sitting in the Technology and Construction Court on March 5, 1999
declaring that the payment into court by London Underground, defendants
in an action brought by Michael Stock, Frances Stock and Kevin Wilcox
(trustees of the Mike Stock Publishing Ltd Retirement and Death Benefit
Scheme) and seven other companies, for damages was ineffective.
The judge ordered that the notice of payment into court on November 4,
1998 be withdrawn.
In 1995 and 1996 London Underground drove tunnels for the Jubilee Line
extension in the vicinity of Hundred House, commercial premises owned by
Michael Stock.
The plaintiffs' case was that as a result the premises were damaged and
a recording studio specially built there became unusable.
Particulars were given of damage to the structure of the building. The
payment-in was to cover the full cost of repairs. There was also a very
much larger claim based on alleged damage to the studio for which £25
million was claimed for consequential losses.
Mr Simon Browne-Wilkinson, QC, for London Underground; Mr Clive
Freedman, QC and Mr Steven Davies for Mr Stock and others.
LORD JUSTICE PILL said that the issue was whether the payment in was in
satisfaction of a cause of action or only part of a cause of action.
In Letang v Cooper ([1965] 1 QB 232, 242) it was said that a cause of
action was simply a factual situation which entitled one party to obtain
from the court a remedy against another person.
London Underground submitted that the claim for damages for loss
occasioned by the cosmetic cracking was a different cause of action from
the claim arising out of the damage to the recording studio, involving
different proof.
Moreover, the nature of the damage was entirely different, being
economic loss in the studio claim. The extent of the alleged damage was
also entirely different.
The rules relating to payment-in should be given a purposive
construction. A broad approach should be adopted: see Steamship Mutual
Underwriting Association Ltd v Trollope and Colls (City) Ltd ((1986) 33
BLR 77).
In determining whether there was a single cause of action, or more than
one cause of action, the fact that the physical damage complained of was
all caused by the same breach of duty, negligent tunnelling, was in his
Lordship's view, a very important factor and in the present case, no
real distinction could be drawn between the mechanisms by which the
different acts of physical damage were caused.
On its facts the case was quite different from Steamship. It was not one
of those building cases where the court had to consider separate
negligent actions arising from separate activities in the course of the
building contract whether by a single wrongdoer or more than one
wrongdoer. His Lordship expressed doubt as to whether the size of a
particular building or its complexities were relevant to the issue.
They did not appear to his Lordship to be relevant in themselves though
they might, as would other factors mentioned in Steamship form the
background against which the relevant issue was to be determined.
His Lordship did not consider Steamship to be authority for the
proposition that where there were heads of damage which were very
different in size and nature that in itself established that there was
more than one cause of action.
While they were dramatically different in size and nature, the different
money claims made in the present case were no more than heads of damage
arising from the same claim. They constituted a composite claim: see
Stewart v Welsh Office (unreported, April 30, 1991) and Hamlin v Edwin
Evans ([1996] PNLR 398).
His Lordship did not consider that a different principle should be
applied to disputes over building contracts from that applied in other
forms of litigation.
His Lordship would accept that the complexities of building operations
were such that they gave more scope for a situation to arise, as in
Steamship, in which the plaintiff could properly be said to have more
than one cause of action.
The court in Steamship was drawing attention to that possibility. The
fact that the heads of damage claimed to result from a claim were
numerous, varied and disparate did not in itself normally create
separate causes of action.
Lord Justice Peter Gibson agreed.
Solicitors: Beachcroft Wansbroughs; Berrymans Lace Mawer, Manchester.

|